05. Completion of Belgrade By-pass, Sector 6, Strazevica-Bubanj Potok

Participant:
Serbia
SEETO No: SEETO CN position:
Corridor X
Transport mode:
Road
Overall project objective:
Belgrade’s bypass highway is a motorway belt being built around Belgrade. In size and significance it is one of the most important infrastructure projects in the Regional Participant. The main route of Corridor X was intersecting Belgrade’s metropolitan area, creating significant traffic problems and congestion on the inner city road network. The idea is to alleviate traffic problems by moving transit away from urban areas onto a new bypass highway. This bypass ring will intersect all motorways leading to Belgrade.
Project benefits:
E K- and accident cost savings. 

xpected benefits include significantly reduced vehicle travel time (international and cross Belgrade journeys), better level of service and less congestion in Belgrade city centre. It will have a great social and economic impact on the wider Belgrade area through improved accessibility and considerably improvement in road safety. The bypass passes through an environmentally sensitive area which will lead to better environmental protection.

Economic / Financial / Environmental indicators:
Decreasing traffic jams in the country of the Belgrade, less emissions in the air, soil, surface and ground wither, decreasing noise levels in the city area.
EIRR: 14.4
OCK: 10%
Total cost (M€) 96.5
Section Type of work Length (km)
 Strazevica-Bubanj Potok  New  9.7

 